Eskom Majuba Power Station
Description: Boiler performance monitoring.
Duration: February 2019 to June 2024
Contact: Duni Rapudi
Details: +27 17 799 3299
Eskom Arnot Power Station
Description: Air Heater air in leakage Test and Pulverized fuel sampling on coal pipes
Duration: May 2021 to May 2026
Contact: Mr. Mulaudzi Mashudu
Details: +27 13 297 9111
Eskom Medupi Power Station
Description: Performance and Testing Services
Duration: January 2021 to December 2025
Contact: Lerato Mogale
Details: +27 14 762 2301
Eskom Kusile Power Station
Description: Provision of Plant Performance Activities
Duration: September 2022 to September 2027
Contact: Siyakudumisa Mpokeli
Details: +27 13 699 7888
Eskom Grootvlei Power Station
Description: Air heater leakage, PF, and Coal Sampling.
Duration: August 2022 to November 2022
Contact: Londiwe Portia Ndwandwe
Details: +27 11 800 8111
Johannesburg Water
Description: Condition Monitoring for bulk wastewater electro-mechanical equipment
Duration: 01 April 2022 to 31 March 2025
Contact: Lawrence Vuyo Mahlangu
Details: 011 959 3903 / +27 78 321 4273